Excavation, roadway boxout, drainage work, metal beam rail installation, and Incident Management System (IMS) installation continues on the Route 2 westbound right shoulder between the Maple Street overpass and the High Street westbound on-ramp. Tree clearing and grubbing continues near the Sutton Avenue eastbound off-ramp.
NoNighttimeWork
Traffic Impacts
Expect partial lane closures or lane reductions near drainage and excavation operations this week. Travel lanes beginning at Maple Street are temporary reduced from 12ft to 11ft while shoulder work is underway.