Construction Updates


  • Weeks 12/2/23 to 1/2/24
    • Day Shift
      • Rte. 2 EB and WB are in there final alignments.
      • Installation of sheet aluminum signs at various locations.
      Night Shift
      • Paving will resume in the spring of 2024
      • Currently installing overhead sign structures and signs.
      • Lighting & IMS is in progress and will continue thru the winter months.
      • New Metal Beam Rail installation is in progress and will continue thru the winter months.
      • Night work will continue weather permitting throughout the winter months.
  • Weeks 11/5/23 to 12/1/23
    • Day Shift
      • Rte. 2 EB and WB are in there final alignments.
      • Landscaping / tree planting is still in progress.
      • Installation of sheet aluminum signs at various locations.
      Night Shift
      • Final paving is finished for this year. Final paving WB from the Hockanum River Bridge west towards Hartford is complete & final paving EB from Hartford to the High Street Bridge is complete. Paving will resume in the spring of 2024
      • Currently installing overhead sign structures and signs.
      • Lighting & IMS is in progress and will continue thru the winter months.
      • New Metal Beam Rail installation is in progress and will continue thru the winter months.
      • Night work will continue weather permitting throughout the winter months.
  • Weeks 9/9/23 to 11/4/23

    Day Shift

    • Rte. 2 EB and WB are currently in there final alignments. All temporary median barrier has been removed.
    • Landscaping / tree planting is in progress – work should be complete by Thanksgiving.
    • All bridge structures are complete.
    • Cleaning existing drainage structures and catch basins.

    Night Shift

    • Final paving in progress. Final paving from the Hockanum River Bridge west towards Hartford should be completed by 11/8/23 both Rte.2 EB and WB.
    • Final paving Rte.2 EB from the Hockanum River Bridge east to Maple Street should be complete by the end of this week.
    • Currently installing overhead sign structures.
    • Lighting & IMS work should resume as soon as the paving is complete.
    • New Metal Bam Rail construction should begin shortly.
    • Night work will continue weather permitting throughout the winter months.

Search


View the latest updates.



Town Hall Presentation
August 19, 2021

CLICK THE MAP below to view live cameras of the project site.

CLICK TO VIEW LIVE WORK ZONE CAMERAS
CLICK TO VIEW CTDOT ROUTE 2 TRAFFIC CAMERAS

View live traffic cameras of the project site.

CLICK TO VIEW LIVE WORK ZONE CAMERAS
CLICK TO VIEW CTDOT ROUTE 2 TRAFFIC CAMERAS