Construction Updates


  • Week of 05/29/2022

    Daytime Hours: 7:00am–3:30pm, Monday-Friday* 

    Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin.

    The retaining wall construction at Willow Street is ongoing. Expect activities on or near the roadway. Concrete form work for bridge elements is on going

    Assembly of the temporary bridge will be begin following the holiday weekend.

    Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday*  Note the earlier starting time

    Work along Route 3 for electrical work will begin. Expect right shoulder closures.

    Line striping for temporary traffic shift on Rte. 2 westbound near Maple Street is expected.

    Traffic Impacts 

    Expect lane closures during overnight electrical work.

    Lane closures, and possibly alternating one-way traffic, may also occur in the vicinity of bridge work this week.

    Due to Holiday Weekend work on Rte. 3 and Rte. 2 is not permitted starting on Friday and continue through Monday.

    *Schedules are subject to change. 

  • Week of 05/22/22

    Daytime Hours: 7:00am–3:30pm, Monday-Friday* 

    Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin.

    The retaining wall construction at Willow Street is ongoing. Expect activities on or near the roadway.

    Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday*  Note the earlier starting time

    Electrical work, including the installation of underground cable and light pole foundations, will shift to eastbound Route 2.

    Median work will continue for preparation and paving operations.

    Work along Route 3 for electrical work will begin. Expect right shoulder closures.

    Holiday Weekend work affecting traffic on Rte. 3 and Rte. 2 is not permitted starting on Friday and extends through Monday. Work off the highways and on local roads is permitted.

    Traffic Impacts 

    Expect right lane closures during overnight electrical work.

    Lane closures, and possibly alternating one-way traffic, may also occur in the vicinity of bridge work this week.

    Left Lane closures for median work should be anticipated.

    *Schedules are subject to change. 

Search


View the latest updates.



Town Hall Presentation
August 19, 2021

CLICK THE MAP below to view live cameras of the project site.

CLICK TO VIEW LIVE WORK ZONE CAMERAS
CLICK TO VIEW CTDOT ROUTE 2 TRAFFIC CAMERAS

View live traffic cameras of the project site.

CLICK TO VIEW LIVE WORK ZONE CAMERAS