Grading/preparation for roadway paving, light pole foundation installation, and catch basin installation will continue east on eastbound (EB) Route 2 between the Sutton Avenue and Maple Street overpasses. Metal guide rail installation will occur on EB Route 2 between the Willow Street overpass and the Exit 5A off-ramp (High Street).
Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday
Catch basin paving and preparation for roadway paving will occur on EB Route 2 between the Willow Street and Maple Street overpasses. Excavation and paving of the Exit 5A westbound (WB) on-ramp (High Street) is also scheduled for this week. Guide rail installation continues project wide. Drainage work will occur in the median and across EB Route 2 between the Willow Street and Ensign Street overpasses.
Traffic Impacts
Expect partial lane closures and lane reductions during construction operations this week.