Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin.
The retaining wall construction at Willow Street is ongoing. Expect activities on or near the roadway. Concrete form work for bridge elements is on going
Assembly of the temporary bridge will be begin following the holiday weekend.
Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday* Note the earlier starting time
Work along Route 3 for electrical work will begin. Expect right shoulder closures.
Line striping for temporary traffic shift on Rte. 2 westbound near Maple Street is expected.
Traffic Impacts
Expect lane closures during overnight electrical work.
Lane closures, and possibly alternating one-way traffic, may also occur in the vicinity of bridge work this week.
Due to Holiday Weekend work on Rte. 3 and Rte. 2 is not permitted starting on Friday and continue through Monday.