week of 7/17/22
July 18, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Ensign Street bridge parapet forming and concrete work continues.
Willow Street Bridge work will involve placing of formwork and reinforcing steel for the deck.
Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck.
Median Barrier installation in the center of Rte. 2 is ongoing.
Retaining wall work (RW101) will commence
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Work along Route 3 for electrical work continues. Expect right shoulder closures.
Maple Street Bridge work is ongoing with activities on and near the road.
Pothole patching on Rte. 2 during the overnight hours should be expected Sunday or Monday Night. Lane closures are required.
Traffic Impacts
Expect lane closures during overnight electrical work and pavement patching operations.