Update (Construction)
week of 8/29/2022
August 22, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Willow Street Bridge work will involve deck demolition
Median Barrier installation in the center of Rte. 2 is ongoing from High Street Bridge to Main Street Bridge.
Work on High Street ramp to install drainage is anticipated
Bridge 374 over the Hokanum River work is on going with parapet rebar and form work.
Traffic Signal work at multiple locations is anticipated
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Roadway milling and concrete pavement work are beginning
Traffic Impacts
The Labor Day Holiday will limit work on the roadway starting on Friday and extending thru Monday night.
Expect lane closures during overnight work.
a minor traffic pattern modification is anticipated at Willow Street.
*Schedules are subject to change