Construction of the EB Sutton Avenue Bridge. Demolition of existing bridge deck is complete. Currently setting structural steel.
Hockanum River Bridge WB – modifications to the right shoulder parapet wall.
Night Shift
Scheduled to mill EB / WB on July 9th between Maple Street and Sutton Avenue for concrete pavement repair.
Scheduled to pave EB on July 11th from the Hockanum River Bridge just to the west of the Willow Street Bridge – area of concrete pavement repair.
Concrete pavement repairs EB from the Hockanum River Bridge just to the west of the Willow Street Bridge.
Quaker on site to drill sign foundations EB for overhead sign sign structures.
Sutton Avenue Daytime Detour – Daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented when necessary for safety reasons during bridge construction. Sutton Avenue will opened for traffic at the end of every workday.