Construction of the EB & WB Sutton Avenue Bridges is complete. The removal of the temporary bridge is complete and the slopes are being graded.
Hockanum River Bridge WB – Modifications to the right shoulder bridge parapet wall is complete.
Quaker on site to drill sign foundations for overhead sign structures.
East River Drive Bridge EB / WB right shoulders – Modifications to the leading ends of the bridge parapet walls are complete.
Enign St. Bridges EB / WB and Main St. Bridge EB right shoulders – Modifications to the leading ends of the bridge parapet walls are in progress – temporary barrier was installed at these locations.
Landscaping is schedued to begin starting on September 18th.
Night Shift
Milling for concrete pavement repair between Sutton Avenue and High Street both EB and WB was performed the week of August 13th. Concrete pavement repairs are proceeding in the same area both EB and WB. This area is scheduled to be paved starting the week of September 17th.