Installation of sheet aluminum signs at various locations.
Night Shift
Final paving is finished for this year. Final paving WB from the Hockanum River Bridge west towards Hartford is complete & final paving EB from Hartford to the High Street Bridge is complete. Paving will resume in the spring of 2024
Currently installing overhead sign structures and signs.
Lighting & IMS is in progress and will continue thru the winter months.
New Metal Beam Rail installation is in progress and will continue thru the winter months.
Night work will continue weather permitting throughout the winter months.