- Weeks 3/1/24 to 4/19/24
Day Shift
– Installing sheet aluminum signs
Night Shift
- Raising catch basins to final grade
- Installing Metal Beam Rail
- Working on the IMS Sytem
- Illumination work is complete
- Scheduled to begin final paving on Sunday Night 4/21
- Starting on 4/21 the Maple St. WB on-ramp will be closed to traffic for approx. one week for full depth reconstruction
- Weeks 12/2/23 to 1/2/24
- Day Shift
- Rte. 2 EB and WB are in there final alignments.
- Installation of sheet aluminum signs at various locations.
- Paving will resume in the spring of 2024
- Currently installing overhead sign structures and signs.
- Lighting & IMS is in progress and will continue thru the winter months.
- New Metal Beam Rail installation is in progress and will continue thru the winter months.
- Night work will continue weather permitting throughout the winter months.
- Day Shift
- Weeks 11/5/23 to 12/1/23
- Day Shift
- Rte. 2 EB and WB are in there final alignments.
- Landscaping / tree planting is still in progress.
- Installation of sheet aluminum signs at various locations.
- Final paving is finished for this year. Final paving WB from the Hockanum River Bridge west towards Hartford is complete & final paving EB from Hartford to the High Street Bridge is complete. Paving will resume in the spring of 2024
- Currently installing overhead sign structures and signs.
- Lighting & IMS is in progress and will continue thru the winter months.
- New Metal Beam Rail installation is in progress and will continue thru the winter months.
- Night work will continue weather permitting throughout the winter months.
- Day Shift