Weeks 6/18/23 to 7/2/23

July 6, 2023 By Jeff Scala

Day Shift

  • Construction of the EB Sutton Avenue Bridge. Demolition of existing bridge deck is complete. Currently setting structural steel.
  • Hockanum River Bridge WB – modifications to the right shoulder parapet wall.

Night Shift

  • Scheduled to mill EB / WB on July 9th between Maple Street and Sutton Avenue for concrete pavement repair.
  • Scheduled to pave EB on July 11th from the Hockanum River Bridge just to the west of the Willow Street Bridge – area of concrete pavement repair.
  • Concrete pavement repairs EB from the Hockanum River Bridge just to the west of the Willow Street Bridge.
  • Quaker on site to drill sign foundations EB for overhead sign sign structures.

Sutton Avenue Daytime Detour – Daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented when necessary for safety reasons during bridge construction. Sutton Avenue will opened for traffic at the end of every workday.