Weeks 9/9/23 to 11/4/23

November 6, 2023 By Jeff Scala

Day Shift

  • Rte. 2 EB and WB are currently in there final alignments. All temporary median barrier has been removed.
  • Landscaping / tree planting is in progress – work should be complete by Thanksgiving.
  • All bridge structures are complete.
  • Cleaning existing drainage structures and catch basins.

Night Shift

  • Final paving in progress. Final paving from the Hockanum River Bridge west towards Hartford should be completed by 11/8/23 both Rte.2 EB and WB.
  • Final paving Rte.2 EB from the Hockanum River Bridge east to Maple Street should be complete by the end of this week.
  • Currently installing overhead sign structures.
  • Lighting & IMS work should resume as soon as the paving is complete.
  • New Metal Bam Rail construction should begin shortly.
  • Night work will continue weather permitting throughout the winter months.