7/11/2022

July 5, 2022 By Jeff Scala
  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
    • Ensign Street bridge parapet form work continues.
    • Willow Street Bridge work will involve setting of steel beams. large overhead equipment are anticipated in the area with temporary road closures.
    • Median Barrier installation in the center of Rte. 2 is ongoing.
    • Work on new drainage outfalls near the Trinity Boat House will continue.
  • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
    • Note the earlier starting time.
    • Work along Route 3 for electrical work continues. Expect right shoulder closures.
    • Hartland Street Bridge work is ongoing with activities on and near the road.
  • Traffic Impacts
    • Expect lane closures during overnight electrical work.*Schedules are subject to change.