Week of April 10, 2022

April 5, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday* 

Construction of the retaining wall located due west of the Sutton Avenue off-ramp continues. Lead removal underneath the Willow Street overpass will continue this week.

Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday* 

Electrical work including the installation of cable, light bases, and light poles continues.

Traffic Impacts 

Expect alternating one-way traffic under the Willow Street overpass during daytime construction operations. Lane closures will occur during night work this week.