Week of 05/22/22

May 20, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday* 

Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin.

The retaining wall construction at Willow Street is ongoing. Expect activities on or near the roadway.

Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday*  Note the earlier starting time

Electrical work, including the installation of underground cable and light pole foundations, will shift to eastbound Route 2.

Median work will continue for preparation and paving operations.

Work along Route 3 for electrical work will begin. Expect right shoulder closures.

Holiday Weekend work affecting traffic on Rte. 3 and Rte. 2 is not permitted starting on Friday and extends through Monday. Work off the highways and on local roads is permitted.

Traffic Impacts 

Expect right lane closures during overnight electrical work.

Lane closures, and possibly alternating one-way traffic, may also occur in the vicinity of bridge work this week.

Left Lane closures for median work should be anticipated.

*Schedules are subject to change.