Update (Construction)
week of 09/26/2022 through 10/8/2022.
September 26, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Willow Street Bridge resetting of steel girders, pour backwalls
Main Street bridge deck demolition
Median Barrier installation in the center of Rte. 2 is ongoing from High Street Bridge to Main Street Bridge.
Bridge 374 over the Hokanum River work is on going with parapet rebar and deck work.
Traffic Signal work at multiple locations is anticipated
Retaining wall construction setting parapets and construction of the slab
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Drainage work in median
milling and concrete pavement work
Light foundations and bases are being places.
Roadway milling and concrete pavement work are beginning this week
Traffic Impacts
Expect lane closures during overnight work.
*Schedules are subject to change