- Daytime Hours: 7:00am–3:30pm, Monday-Friday
- Willow Street Bridge work on forming deck
- Main Street bridge deck demolition
- Retaining Wall work is ongoing with closure pours of the parapets and moment stabs
- Bridge 374 over the Hockanum River work is ongoing with parapet rebar and deck work.
- Traffic Signal work at multiple locations is anticipated
- Retaining wall construction setting parapets and construction of the slab
- Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
- Note the earlier starting time.
- Drainage work in median
- milling and concrete pavement work which requires closing of some lanes
- Light foundations and bases are being places near East River Drive.
- Installation of light poles
- Traffic Impacts
- Expect lane closures during overnight work.
- *Schedules are subject to change
Week of 10/31/22
- Daytime Hours: 7:00am–3:30pm, Monday-Friday
- Willow Street Bridge work on forming deck
- Main Street bridge deck demolition
- Bridge 374 over the Hockanum River work is ongoing with parapet rebar and deck work.
- Traffic Signal work at multiple locations is anticipated
- Retaining wall construction setting parapets and construction of the slab
- Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
- Note the earlier starting time.
- Drainage work in median
- milling and concrete pavement work which requires closing of some lanes
- Installation of light poles
- Traffic Impacts
- Expect lane closures during overnight work.
- *Schedules are subject to change