Update (Construction)
Week of 11/6/22
October 31, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Willow Street Bridge work is ongoing
Main Street bridge work is ongoing
Retaining Wall work is ongoing with backfilling activities
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Relocation of Temporary Barriers
Light pole installation
Traffic Impacts
Expect lane closures during overnight work.
*Schedules are subject to change