Update (Construction)
Week of 3/12 – 3/25
March 13, 2023
By
Jeff Scala
Day Shift:
Willow Street eastbound on ramp:
Work in the area involves excavation and grading in the gore area, with heavy equipment and large trucks present.
Sutton Ave Bridge Location:
Ongoing work at this location is to prepare the temporary bridge required for stage construction on Route 2
Route 2 over Main Street Bridge:
Contractor will be working on the bridge supports with personnel and equipment adjacent to the local road.
Night Shift
No Work is planned.