  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
    • Ensign Street bridge parapet forming and concrete work continues.
    • Willow Street Bridge work will involve setting of steel beams. large overhead equipment are anticipated in the area with temporary road closures.
    • Bridge 374 over the Hokanum River work is on going
    • Median Barrier installation in the center of Rte. 2 is ongoing.
    • Work on new drainage outfalls near the Trinity Boat House will continue.
    • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
      • Note the earlier starting time.
      • Work along Route 3 for electrical work continues. Expect right shoulder closures.
      • Hartland Street Bridge work is ongoing with activities on and near the road.
    • Traffic Impacts
      • Expect lane closures during overnight electrical work