week of 7/17/22

July 18, 2022 By Jeff Scala
  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
      • Ensign Street bridge parapet forming and concrete work continues.
      • Willow Street Bridge work will involve placing of formwork and reinforcing steel for the deck.
      • Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck.
      • Median Barrier installation in the center of Rte. 2 is ongoing.
      • Retaining wall work (RW101) will commence
    • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
      • Note the earlier starting time.
      • Work along Route 3 for electrical work continues. Expect right shoulder closures.
      • Maple Street Bridge work is ongoing with activities on and near the road.
      • Pothole patching on Rte. 2 during the overnight hours should be expected Sunday or Monday Night. Lane closures are required.
    • Traffic Impacts
      • Expect lane closures during overnight electrical work and pavement patching operations.
    • .*Schedules are subject to change.