week of 7/24/22

July 22, 2022 By Jeff Scala
  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
    • Ensign Street bridge parapet forming and concrete placement anticipated.
    • Willow Street Bridge work will involve placing of formwork and reinforcing steel for the deck and setting up equipment.
    • Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck.
    • Median Barrier installation in the center of Rte. 2 is ongoing.
    • Retaining wall work (RW101) will continue with footing work.
  • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
    • Note the earlier starting time.
    • Work along Route 3 for electrical work continues. Expect right shoulder closures.
    • Median drainage work is being performed.
  • Traffic Impacts
    • Expect lane closures during overnight electrical work and pavement patching operations.
    • *Schedules are subject to change.