Ensign Street bridge deck form work continues. Lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving are ongoing.
Median Barrier installation in the center of Rte. 2 is ongoing.
Demolition and other construction at Willow Street is ongoing. Expect activities on or near the roadway.
Work on new drainage outfalls near the Trinity Boat House will be performed.
Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Work along Route 3 for electrical work continues. Expect right shoulder closures.
Hartland Street Bridge work is ongoing with activities on and near the road.
Traffic Impacts
Expect lane closures during overnight electrical work.*Schedules are subject to change.
4th of July Holiday weekend limits work on the highway between Friday and Tuesday morning.