week of 8/15/22
August 9, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Willow Street Bridge work will involve placing rebar and concrete for the keeper blocks
Ensign Bridge waterproof membrane is to be installed in preparation of bituminous overlay
Bridge 374 over the Hokanum River work is on going with parapet rebar and form work.
Median Barrier installation in the center of Rte. 2 is ongoing.
Retaining wall work (RW101) will continue with footing work.
Riverside Drive drainage work is expected
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Work along Route 3 for electrical work continues. Expect right shoulder closures.
Backfilling of retaining wall is ongoing.
Median paving is anticipated.
Traffic Impacts
Expect lane closures during overnight electrical work.