Week of 8/21/2022

August 22, 2022 By Jeff Scala
  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
    • Willow Street Bridge work will involve deck demolition
    • Riverside Drive drainage work is ongoing
    • Median Barrier installation in the center of Rte. 2 is ongoing from High Street Bridge to Main Street Bridge.
    • Work on High Street ramp to install drainage is anticipated
    • Bridge 374 over the Hokanum River work is on going with parapet rebar and form work.
    • Traffic Signal work at multiple locations is anticipated
    • Retaining wall work (RW101) will continue with footing work.
  • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
    • Note the earlier starting time.
    • Paving in the median of Rte. 2
    • Paving of several ramps
    • Drainage work is ongoing.
  • Traffic Impacts
    • Expect lane closures during overnight work.
    • a minor traffic pattern modification is anticipated at Willow Street.
    • *Schedules are subject to change