Week of 8/7/2022
August 9, 2022
By
Jeff Scala
Daytime Hours
: 7:00am–3:30pm, Monday-Friday
Willow Street Bridge work will involve placing rebar and concrete for the parapets.
Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck.
Median Barrier installation in the center of Rte. 2 is ongoing.
Retaining wall work (RW101) will continue with footing work.
Riverside Drive utility work will continue.
Nighttime Hours
: 6:00pm–6:00am, Sunday-Thursday
Note the earlier starting time.
Work along Route 3 for electrical work continues. Expect right shoulder closures.
Backfilling of retaining wall is ongoing.
Traffic Impacts
Expect lane closures during overnight electrical work.
*Schedules are subject to change.