week of 9/4/22

September 6, 2022 By Jeff Scala
  • Daytime Hours: 7:00am–3:30pm, Monday-Friday
    • Main Street Bridge demolition of decks
    • Median Barrier installation in the center of Rte. 2 is ongoing from High Street Bridge to Main Street Bridge.
    • Bridge 374 over the Hokanum River work is on going with parapet rebar and form work.
    • Traffic Signal work at multiple locations is anticipated
  • Nighttime Hours: 6:00pm–6:00am, Sunday-Thursday
    • Note the earlier starting time.
    • Traffic shift on Rte. 2 is expected.
    • Light foundations and bases are being places.
    • Roadway milling and concrete pavement work are beginning next week
    • Traffic Impacts
      • The Labor Day Holiday will limit work on the roadway starting on Friday and extending thru Monday night.
      • Expect lane closures during overnight work.
      • a minor traffic pattern modification is anticipated at Willow Street.
      • *Schedules are subject to change