Week of April 3, 2022

April 5, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday* 

Construction of the retaining wall located due west of the Sutton Avenue off-ramp continues. Installation of the pre-cast barrier within the median between the High Street and Ensign Street overpasses is scheduled to occur. Lead removal underneath the Ensign Street overpass will be completed and the demolition and removal of the Ensign Street bridge deck will begin this week. Lead removal will begin underneath the Willow Street overpass and is scheduled to continue into next week.

Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday* 

Electrical work including the installation of cable, light bases, and light poles will occur.

Traffic Impacts 

Expect alternating one-way traffic under the Ensign Street and Willow Street overpasses during daytime construction operations. Lane closures will occur during night work this week.

*Schedules are subject to change.