Week of August 15, 2021

August 15, 2021 By Jeff Scala

Work Schedule*

Daytime Hours: 7:00am–3:30pm, Monday-Friday

Curb installation continues west of the Sutton Avenue overpass. Tree clearing and grubbing will occur near the Riverside Magnet School.

Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday

Underground conduit installation continued on Route 2 across various on-ramps on the westbound side. Roadway excavation will occur on Route 2 behind the barrier on the westbound right shoulder.

Traffic Impacts

Expect partial lane closures or lane reductions near excavation operations this week. Travel lanes beginning at Maple Street are temporary reduced from 12ft to 11ft while shoulder work is underway.

*schedules are subject to change