Week of March 20, 2022

March 21, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday

Precast concrete barrier installation will occur on Route 2 Eastbound between the Ensign Street and Main Street overpasses. Demolition of the High Street overpass parapet is also scheduled for this week. Work will occur on pipe jacking pits in the vicinity of Goodwin College. Decking installation will occur under the Ensign overpass. Lead removal underneath the Ensign Street, Willow Street, and Sutton Avenue overpasses is tentatively scheduled.

Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday* 

No night work is scheduled for this week. 

Traffic Impacts 

No major traffic impacts are expected. 

*Schedules are subject to change.