Work Schedule*
No construction operations will occur this week after 6:00am on Wednesday, November 24th.
Construction operations are scheduled to resume after 6:00am on Monday, November 29th.
Daytime Hours: 7:00am–3:30pm, Monday-Tuesday
Drainage work will occur on Route 2 in the median between the Willow Street and High Street overpasses.
Nighttime Hours: 7:00pm–6:00am, Monday-Wednesday
Drainage work will continue on Route 2 in the median between the Willow Street and High Street overpasses.
Traffic Impacts
No major traffic impacts are expected.
*Schedules are subject to change.