Week of November 14, 2021

November 7, 2021 By Jeff Scala

Work Schedule*

Daytime Hours: 7:00am–3:30pm, Monday-Friday

Information Management System (IMS) installation continues within the project limits.

Nighttime Hours: 7:00pm-6:00am, Sunday-Thursday

Roadway paving will occur on EB Route 2 between the Sutton Avenue and Maple Street overpasses; line-striping/safety markings is tentatively scheduled for the same area on EB Route 2. The barrier on the WB Route 2 shoulder will be relocated to accommodate moving construction operations and the upcoming lane shift. Guide rail installation continues.

Traffic Impacts

Expect partial lane closures and lane reductions during construction operations this week.

*Schedules are subject to change.