Curb and metal guide rail installation will occur on EB Route 2 between the Willow Street and Maple Street overpasses.
Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday
Roadway paving will occur on EB Route 2 between the Sutton Avenue and Maple Street overpasses. Guide rail installation continues project wide. Excavation will continue this week on EB Route 2 between the Exit 5B off-ramp (Sutton Avenue) and the Exit 5C off-ramp (Maple Street). The barrier on the WB Route 2 shoulder will be relocated to accommodate moving construction operations and the upcoming lane shift.
Traffic Impacts
Expect partial lane closures and lane reductions during construction operations this week.