Weeks 6/4/23 to 6/17/23

June 12, 2023 By Jeff Scala

Day Shift

  • Construction of WB Sutton Avenue Bridge. Place concrete for the bridge deck and the parapet walls.
  • Finish the surface of the cast-in-place Hockanum River Bridge WB parapet wall.

Night Shift

  • Pave WB from the Ensign Street Bridge to the Hockanum River Bridge.
  • Mill EB down to the concrete pavement from the Hockanum River Bridge just to the west of the Willow Street Bridge for concrete pavement repairs.
  • Concrete pavement repairs EB from Hockanum River Bridge just to the west of the Willow Street Bridge.
  • Ducci Electric on site to install fiberglass conduit on the underside of bridges.
  • Quaker on site to drill sign foundations WB for overhead sign sign structures.

Sutton Avenue Daytime Detour – Starting the week of April 24, 2023, daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented when necessary for safety reasons during construction. The detour will be during daytime construction hours from 7am to 4pm. Sutton Avenue will be opened to traffic at the end of construction everyday.