Day Shift:

  • Sutton Avenue Temporary Bridge: Contractor will be installing forms and placing concrete for the bridge approach slabs, constructing the roadway base and placing asphalt in preparation of the Route 2 WB traffic shift.
  • Overhead sign Foundations – Construction of overhead sign foundations WB between Willow Street and Pitkin Street – expect lane closures between the hours of 9am and 3pm.
  • Median Barrier – Placement of permanent precast concrete barrier sections between Main Street and High Street

Project Wide:

  • Median barrier concrete pours are planned to close the gaps in the median barrier.

Night Shift:

  • Nightly traffic patterns are required to perform concrete pavement repairs on Route 2 Eastbound between Willow and High Streets – expect lane closures
  • Pavement placement work in median areas near Willow Street – expect lane closures
  • Rte. 2 WB traffic shift onto the temporary bridge at Sutton Avenue is scheduled for Sunday night 4/23/23