Author: Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Drainage work is scheduled to occur in the median on Route 2 between the Willow Street overpass and the Main Street overpass. Nighttime Hours: 7:00pm–6:00am, Monday-Friday Information Management System (IMS) installation will continue on Route 3 within the project limits. Guide rails will be installed on the westbound shoulder […]

December 6, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday No daytime construction work is scheduled to occur this week. The permanent closures of both the Route 2 eastbound (EB) Sutton Avenue off-ramp (Exit 5B) and the Route 2 westbound (WB) Cambridge Drive on-Ramp (Exit 5B) have been postponed until January 17, 2022. Nighttime Hours: 7:00pm–6:00am, Monday-Friday Information Management […]

December 1, 2021 By Jeff Scala

Work Schedule* No construction operations will occur this week after 6:00am on Wednesday, November 24th. Construction operations are scheduled to resume after 6:00am on Monday, November 29th. Daytime Hours: 7:00am–3:30pm, Monday-Tuesday Drainage work will occur on Route 2 in the median between the Willow Street and High Street overpasses. Nighttime Hours: 7:00pm–6:00am, Monday-Wednesday Drainage work […]

November 22, 2021 By Jeff Scala

The Connecticut Department of Transportation is announcing the permanent closures of both the Route 2 Eastbound Sutton Avenue off-ramp (Exit 5B) and Route 2 Westbound Cambridge Drive on-ramp (Exit 5B). As part of the safety and operational improvements on Route 2, permanent ramp closures are necessary in the Town of East Hartford. Improvements associated with […]

November 11, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Information Management System (IMS) installation continues within the project limits. Nighttime Hours: 7:00pm-6:00am, Sunday-Thursday Roadway paving will occur on EB Route 2 between the Sutton Avenue and Maple Street overpasses; line-striping/safety markings is tentatively scheduled for the same area on EB Route 2. The barrier on the WB Route […]

November 7, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Information Management System (IMS) installation continues within the project limits. Guiderail installation continues on eastbound (EB) Route 2 from the Sutton Avenue overpass to the end of the project limits at Maple Street. Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday Guide rail installation continues. Curb installation and roadway paving will occur on […]

November 7, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Curb and metal guide rail installation will occur on EB Route 2 between the Willow Street and Maple Street overpasses. Nighttime Hours: 7:00pm–6:00am, Sunday-Thursday Roadway paving will occur on EB Route 2 between the Sutton Avenue and Maple Street overpasses. Guide rail installation continues project wide. Excavation will continue […]

October 26, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Grading/preparation for roadway paving, light pole foundation installation, and catch basin installation will continue east on eastbound (EB) Route 2 between the Sutton Avenue and Maple Street overpasses. Metal guide rail installation will occur on EB Route 2 between the Willow Street overpass and the Exit 5A off-ramp (High […]

October 26, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday Grading/paving preparation and light pole foundation installation will occur on eastbound (EB) Route 2 between the Exit 5B off-ramp (Sutton Avenue) and the Exit 5C off-ramp (Maple Street). Nighttime Hours: 7:00pm-6:00am, Sunday-Thursday Excavation will continue this week on EB Route 2 between the Exit 5B off-ramp (Sutton Avenue) and […]

October 12, 2021 By Jeff Scala

Work Schedule* Daytime Hours: 7:00am–3:30pm, Monday-Friday The following operations are scheduled to move forward on eastbound (EB) Route 2 between the Ensign Street overpass and Exit 5A (High Street): grading and preparation for roadway paving, light pole foundation and metal beam rail installation. Nighttime Hours: 7:00pm-6:00am, Sunday-Thursday Roadway excavation continues on EB Route 2 between […]

October 3, 2021 By Jeff Scala