Author: Jeff Scala
Day Shift Night Shift Sutton Avenue Daytime Detour – Daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented when necessary for safety reasons during bridge construction. Sutton Avenue will opened for traffic at the end of every workday.
Sutton Ave bridge WB – install rebar Sutton Ave bridge WB – install rebar Sutton Ave bridge WB – place concrete for deck Sutton Ave bridge WB – place concrete for deck Sutton Ave bridge WB – place concrete for parapet
Day Shift Night Shift Sutton Avenue Daytime Detour – Starting the week of April 24, 2023, daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented when necessary for safety reasons during construction. The detour will be during daytime construction hours from 7am to 4pm. Sutton Avenue will be opened to traffic […]
Day Shift
Sutton Ave – Unload new steel girders Sutton Ave. – Unloading new steel girders Sutton Avenue Bridge Foundation for new camera pole Sutton Ave Bridge – Deck Pans Sutton Ave. Bridge – Steel supports for utilities
Sutton Avenue Temporary Bridge Pave Sutton Ave Temporary Bridge Pave Sutton Ave Temporary Bridge Demolition of Sutton Ave WB Bridge Demolition of Sutton Ave WB Bridge Demolition of Sutton Ave WB Bridge Drilled Shaft for CCTV foundation
Day Shift
Day Shift Night Shift
Starting the week of April 24, 2023, daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented to demolish the existing WB bridge. The detour will be will marked. The detour will be weather dependent and last a few weeks. The detour will be during daytime construction hours from 7am to 4pm. […]
The Maple Street WB On-ramp will be closed to all traffic for full-depth roadway reconstruction starting on Sunday night 4/21 and is tentatively scheduled to reopen on Friday 4/26. Traffc will be detoured to Main Street and then to the Rte. 2 WB on-ramp at High Street. DOT Project No. 0042-0317 was awarded to Empire […]