Sutton Ave – Unload new steel girders Sutton Ave. – Unloading new steel girders Sutton Avenue Bridge Foundation for new camera pole Sutton Ave Bridge – Deck Pans Sutton Ave. Bridge – Steel supports for utilities

May 22, 2023 By Jeff Scala

Sutton Avenue Temporary Bridge Pave Sutton Ave Temporary Bridge Pave Sutton Ave Temporary Bridge Demolition of Sutton Ave WB Bridge Demolition of Sutton Ave WB Bridge Demolition of Sutton Ave WB Bridge Drilled Shaft for CCTV foundation

May 9, 2023 By Jeff Scala

Day Shift Night Shift

April 26, 2023 By Jeff Scala

Starting the week of April 24, 2023, daytime closures of Sutton Avenue at the Rte. 2 bridge will be implemented to demolish the existing WB bridge. The detour will be will marked. The detour will be weather dependent and last a few weeks. The detour will be during daytime construction hours from 7am to 4pm. […]

April 17, 2023 By Jeff Scala

The construction of the Sutton Avenue EB and WB bridges are complete.  The Rte.2 EB traffic was diverted back onto the new EB bridge on August 6th and the WB traffic was diverted off the temporary bridge and onto the new WB bridge on August 10th. DOT Project No. 0042-0317 was awarded to Empire Paving […]

April 11, 2023 By Jeff Scala

Day Shift: Project Wide: Night Shift:

April 11, 2023 By Jeff Scala

Day Shift: Night Shift

March 13, 2023 By Jeff Scala