Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge deck form work continues. Lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving are ongoing. Median Barrier installation in the center of Rte. 2 is ongoing. Demolition and other construction at Willow Street is ongoing. Expect activities on or near the […]

July 1, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge deck form work continiuesLead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving are ongoing. The retaining wall construction at Willow Street is ongoing. Expect […]

June 30, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday* Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge deck form work continiues Lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at Willow Street […]

June 20, 2022 By Jeff Scala

Week of 06/12/22Daytime Hours: 7:00am–3:30pm, Monday-Friday* Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge deck form work begings. Lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at […]

June 13, 2022 By Jeff Scala

The Connecticut Department of Transportation is announcing a lane shift of Route 2 EB prior to the Exit 5 off-ramp (Willow Street) beginning on June 16, 2022.  The temporary lane shift of Route 2 EB prior to Exit 5 off-ramp (Willow Street) is necessary as part of the safety and operational improvements on Route 2 […]

June 10, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday*  Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at Willow Street is ongoing. […]

June 3, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday*  Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at Willow Street is ongoing. […]

May 23, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday*  Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at Willow Street is ongoing. […]

May 20, 2022 By Jeff Scala

The Connecticut Department of Transportation is announcing the closure of the East Coast Greenway Multi-Use Trail at Willow Street will begin on May 31, 2022.  The temporary closure of the multi-use trial at Willow Street is necessary as part of the safety and operational improvements on Route 2 in East Hartford, Hartford, and Glastonbury. The […]

May 17, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday*  Retaining wall construction continues along the right shoulder on eastbound Route 2 just prior to Sutton Avenue. Ensign Street bridge demolition and lead paint removal underneath the Sutton Avenue and Main Street bridges will continue. Additional activities involving the bridges will begin. The retaining wall construction at Willow Street is ongoing. […]

May 16, 2022 By Jeff Scala