Author: Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Willow Street Bridge work will involve placing rebar and concrete for the keeper blocks Ensign Bridge waterproof membrane is to be installed in preparation of bituminous overlay Bridge 374 over the Hokanum River work is on going with parapet rebar and form work. Median Barrier installation in the center of Rte. […]

August 9, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Willow Street Bridge work will involve placing rebar and concrete for the parapets. Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck. Median Barrier installation in the center of Rte. 2 is ongoing. Retaining wall work (RW101) will continue with […]

August 9, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge removing of construction forms. Willow Street Bridge work will involve placing of formwork for the parapets. Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck. Median Barrier installation in the center of Rte. 2 is ongoing. Retaining […]

August 9, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge parapet forming and concrete placement anticipated. Willow Street Bridge work will involve placing of formwork and reinforcing steel for the deck and setting up equipment. Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck. Median Barrier installation […]

July 22, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge parapet forming and concrete work continues. Willow Street Bridge work will involve placing of formwork and reinforcing steel for the deck. Bridge 374 over the Hokanum River work is on going with removal of the parapet and section of the deck. Median Barrier installation in the center of […]

July 18, 2022 By Jeff Scala

The Connecticut Department of Transportation is announcing the temporary ramp closure of the High Street On-Ramp (Exit 5A)to Route 2 Eastbound beginning on August 7, 2022, weather permitting.  The temporary ramp closure of the High Street On-Ramp (Exit 5A) toRoute 2 EB is necessary as part of the safety and operational improvements on Route 2 […]

July 14, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge parapet forming and concrete work continues. Willow Street Bridge work will involve setting of steel beams. large overhead equipment are anticipated in the area with temporary road closures. Bridge 374 over the Hokanum River work is on going Median Barrier installation in the center of Rte. 2 is […]

July 12, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge parapet forming and concrete work continues. Willow Street Bridge work will involve setting of steel beams. large overhead equipment are anticipated in the area with temporary road closures. Bridge 374 over the Hokanum River work is on going Median Barrier installation in the center of Rte. 2 is […]

July 12, 2022 By Jeff Scala

Daytime Hours: 7:00am–3:30pm, Monday-Friday Ensign Street bridge parapet form work continues. Willow Street Bridge work will involve setting of steel beams. large overhead equipment are anticipated in the area with temporary road closures. Median Barrier installation in the center of Rte. 2 is ongoing. Work on new drainage outfalls near the Trinity Boat House will […]

July 5, 2022 By Jeff Scala